Electrical Engineering

6.6kV Switchboard same day install at Belfast Harbour

Last weekend at Belfast Harbour we installed a 6.6kV Schneider Ringmaster 6 piece switchboard using CE6 Incomer and CE2 Outgoers to replace a Long & Crawford GF3 Oil Switchboard and Merlin Gerin RM6 Switchboard. All stripe out, installation and cable jointing works completed same day within 14 hours. Old switchboards isolated and proved dead at 8:30am, new switchboard made live and fully operational at 10:00Pm.

If you require any further information on the products or services that we offer you can contact us at +44(0)28867 62295 or at sales@jjloughran.com

Project Details

Date:

February 21 2022


Category:

Electrical Engineering